+234 (0)80–35082614, +234 (0)70–35557575, info@enikkom.com

Project Highlight

Expansion of Escravos-Lagos Gas Pipeline Project – Phase II; Installation of 36inch x 10km pipeline sections by Horizontal Directional Drilling (HDD).

Scope of Project

  • Installation of 36inch x 2km pipeline by Horizontal Directional Drilling (HDD) across swamps and built up/encroachment areas (KP 317+445 to KP 319+880).
  • Installation of 36inch x 600m pipeline by Horizontal Directional Drilling (HDD) across Lagos/Ibadan express road (KP 317 + 500).
  • Installation of 36inch x 2.8km pipeline by Horizontal Directional Drilling (HDD), across Ogun River and adjoining swamp (KP 322 + 604 to KP 325 + 247 ).
  • Installation of 36inch x 1.9km pipeline by Horizontal Directional Drilling (HDD) across built up/encroachment areas (KP 325+700 to KP 327+600).
  • 7.2km of phase 1 of HDD works completed.
PROECT NAME:

Expansion of Escravos-Lagos Gas Pipeline Project – Phase II

CLIENT:

NNPC/Zakhem Construction Nigeria Limited.

SUBCONTRACTOR:

Enikkom Construction Limited

PROJECT STATUS:

Phase 1 completed.